<< Click to Display Table of Contents >> Batch Date Manager |
Copyright © 2019 EarthSoft, Inc • Modified: 18 Feb 2019 |
![]() |
The Batch Date Manager allows for the exclusion of dates across all facilities using the user's customized date list.
1.Select the desired facilities to which the exclusion will be applied.
2.Select the Plans and Tasks to which the exclusion will be applied.
3.Select the mode and load the file with dates. To create a file with the list of dates, refer to the article Define Task Dates which explains how to offset days, skip months, and set custom dates.
4.After the files with dates are loaded, click Apply to finish.