Batch Date Manager

<< Click to Display Table of Contents >>

Navigation:  SPM > SPM > Forms >

Batch Date Manager

The Batch Date Manager allows for the exclusion of dates across all facilities using the user's customized date list.

 

1.Click Batch Date Manager in the Forms group of the Plan ribbon to open the SPM Batch Date Manager window.

SPM-Plan_Ribbon-Forms_Group

2.Select the desired facilities to which the exclusion will be applied.

SPM-Batch_Date_Manager

3.Select the Plans to which the exclusion will be applied.

4.Select the Tasks to which the exclusion will be applied.

5.Select the mode and load the file with dates. To create a file with the list of dates, refer to the article Define Task Dates which explains how to offset days, skip months, and set custom dates.

SPM-Batch_Date_Manager4

6.After the file with dates are loaded, click Apply to finish.